Monday, 18 December 2017

18.12.17 - Frames completed and windows installed

The frames were completed today and all of the windows and sliding door installed.








Friday, 15 December 2017

15.12.17 - Frames

The frames started going up on Friday and should hopefully be finished early this week for the roof to start going on. We are very happy with the size of all rooms, especially the big open plan kitchen/family/dining area which opens out to the alfresco.







Saturday, 9 December 2017

9.12.17 - Slab poured

The concrete slab was poured this morning and all timber form work removed. 








Thursday, 7 December 2017

7.12.17 - Forming up and waffle pods

Waffle pods put in and the rest of the forming up was completed today, ready for the concrete pour on Friday!

Wednesday, 6 December 2017

6.12.17 - Plumbing and form work

The waste plumbing was completed yesterday and more forming up done today. The waffle pods have also been delivered and should be installed tomorrow on 7th Dec, ready for the slab to be poured on Friday 8th Dec. It's good to start seeing the size of the house and where everything will be.







Monday, 4 December 2017

4.12.17 - Piering

All of our piering was completed today. We had an allowance in the contract for 80 lineal metres, but they only used 49, due to some rock below the surface which stabilised the pad. Forming up of the slab also begun.