Friday, 30 March 2018

30.3.18 Officially locked out

Front door, laundry door and garage internal door have been put on and we are officially locked out! They have also put all the internal doors on.







Thursday, 22 March 2018

22.3.18 Plastering and waterproofing done

All the cornice and plastering is done, very tidy job. They have also waterproofed the laundry and bathrooms.





Monday, 12 March 2018

12.3.18 Gyprock done

All the sheets for ceiling and walls have been put in. We are so happy that we added high ceilings and doors...makes the rooms look huge!











12.3.18 Excavation done for water tanks and septic

We hired an earthworks guy to come and clear a spot for our 2x 25,000L water tanks, as well as dig the hole for our septic tanks. He did hit rock during the septic hole dig and we had to hire a rock breaker to get through it.



Thursday, 1 March 2018

1.3.2018 Electrical trenching and conduit

The electrical trench was done today. Our contract allowed a large provision for this trench, as whoever developed our block put the green electrical box on the opposite side of our 4 acre block! The second picture is the trench all filled in again.